When do you need a PPC certificate?

  • New Installation: after the completion of the construction of each electrical installation and before it is put into operation by the user.
  • Modification of Installation: after the extension or modification of an electrical installation (e.g. new supplies, request for an increase in installation power, change from single-phase to three-phase, etc.) and before it is put into operation by the user.
  • Site Supply: for electrification of a site supply.
  • Re-inspection: after the intervals specified by law for each category of installation. The aim is to verify that the degree of safety provided by the electrical installation has not been reduced due to wear or damage or general deterioration of the electrical material from any cause. If problems are identified, the electrician must make the necessary corrections in order to issue the Installer’s Declaration of Compliance.

 The Required Documents  For  New PPC Certificate:

  • Declaration of Licensed Electrical Installer
  • Electrical Installation Delivery Report
  • Electrical Installation Control Protocol according to ELOT HD 6364 or according to KEEEE (for installations before March 2006)
  • Single-line drawing of the electrical panel of the installation
  • Plan of the installation, showing the routing of the electrical lines and the location of the panel, electrical devices, switches, luminaires, sockets, motors, etc.

The required documents are completed entirely by us.

What is needed from your side:

  • Contact a licensed electrical installer. Contact us, let us know the details of your installation and receive our offer.
  • Have the supply number of the installation available. The supply number is written on the PPC bill and on the meter (“clock”) at the entrance of the installation/apartment.
  • Give us access to your premises by appointment to make the necessary installation check.
  • Receive the certified Installer’s Declaration of Responsibility (ICD – PPC Certificate) from us and submit it to the electricity provider of your choice.